Application Details   Print
From :   M/s BHUNIT ENGINEERING CO. PVT. LTD. (13FDBB582706)
No :   3588096 Date :   27/04/2017 10:28:47
Sub :   Application For - CTO / both/HWM / new

Activity:
Forward   
Description
Please check and put up
Activity:
Verification  
Description
Please check and put up
Note By: Vijay Chaudhary (Regional Officer)
Date Time: 28/04/2017 11:34:54 AM
Forwarded To: AEE I

Activity:
Forward   
Description
After verification of the application form the following deficiencies wee found 1. not submitted the copy of latest A/R of Air emission from stack 2. not submitted the agreement with registered oil recycler 3. not submitted the HWM return 4. not submitted the noise monitoring report of DG set .5.not submitted the additional details in the application form 6.not submitted the proper CA certificate as per the previous .7. not submitted the consent fee and Performance security as per the polict of the Board .pls issue the SCN to the unit .
Note By: Vipin Kumar (AEE I)
Date Time: 01/05/2017 14:45:39 PM
Forwarded To: Regional Officer

Activity:
Forward   
Description
Activity:
Show Cause (Send To Industry)    |   Reminder    |       |      View SCN (both/HWM) For Refusal 
Description
Note By: Vijay Chaudhary (Regional Officer)
Date Time: 08/05/2017 12:57:29 PM
Forwarded To: AEE I

Activity:
Forward    View Document
Description
BECPL/HSPCB/2017 To Date :- 20.05.2017 The Regional officer Haryana State pollution Control Board Ballabgarh Region Faridabad -2, Haryana Subject : Show cause notice 017FDBBCTOA/W/HWMSCN3588096 dated – 08.05.2017 Dear Sir This is reference to above said show cause notice 017FDBBCTOA/W/HWMSCN3588096 dated – 20.05.2017. we would like to have your kind attention on followings. 1. We have submitted the fees for stack Air emission sample testing therefore You are requested to collect the sample for testing. 2. Enclosing herewith copy of agreement with registered oil recycler. 3. Enclosing herewith copy of HWM return. 4. We have submitted the fees for Noise pollution testing therefore You are requested to coolect the sample for testing. 5. We have submitted the additional details in the application. 6. Enclosing herewith copy of CA certificate as per the previous. 7. Enclosed herewith performance security original DD( NO - 491845) of Rs – 200000/- dated 18/05/2017 in favor of Haryana state pollution control board. 8. We have submitted the CTO fees for one year vide DD No – 491741 dated 26.04.2017 of Rs -125700/- as detail mention below :- Consent fees air for one year – 15000X 1 = 15000/- Consent fees water for one year – 15000X 1 = 15000/- Consent Late fees (300%) for air – 15000X 300% = 45000/- Consent Late fees (300%) for water – 15000X 300% = 45000/- Air sample testing fees for one year – 2700X 1 = 2700/- Noise pollution testing fees for 3 nos DG Set – 1000X 3 = 3000/- Total fees = 125700/- Kindly acknowledge the receipt of the same & instruct the concern person to collect the sample. Thanking You, Yours faithfully, For Bhunit Engineering Co. Pvt. Ltd
Note By: 13FDBB582706 (Industry)
Date Time: 20/05/2017 12:32:55 PM
Forwarded To: AEE I

Activity:
Forward   
Description
Due to transfer, please forwarded the case to the concerned area incharge.
Note By: Vipin Kumar (AEE I)
Date Time: 10/07/2017 10:30:47 AM
Forwarded To: Regional Officer

Activity:
Forward   
Description
Please submit recommendation.
Note By: Vijay Chaudhary (Regional Officer)
Date Time: 24/07/2017 18:30:35 PM
Forwarded To: AEE II

Activity:
Forward   
Description
Reply submitted by the unit is not satisfactory. SCN may be issued to the unit- 1. Not submitted the agreement with registered oil recycler. 2. Not submitted the HWM return. 3. Not submitted the proper CA certificate as per the previous. The case may be sent to H.O for permission to collect the samples as the unit has deposited the testing fees with the Board.
Note By: Smita Kanodia (AEE II)
Date Time: 27/07/2017 10:29:44 AM
Forwarded To: Regional Officer

Activity:
Forward   
Description
As per policy of the Board, unit has deposited the sample fees under Water / Air Act & Noise Rules. Kindly grant the permission for collection of samples.
Activity:
Show Cause (Send To Industry)    |   Reminder    |       |      View SCN (both/HWM) For Refusal 
Description
Note By: Vijay Chaudhary (Regional Officer)
Date Time: 28/07/2017 16:45:56 PM
Forwarded To: SEE II

Activity:
Forward   
Description
May allow RO for inspection & collection of sample as requested by him.
Note By: Chand Saini (SEE II)
Date Time: 30/07/2017 20:36:44 PM
Forwarded To: MS

Activity:
Forward   
Description
Permission granted for inspection and collection of samples, as proposed
Note By: S Narayanan IFS (MS)
Date Time: 31/07/2017 07:02:42 AM
Forwarded To: SEE II

Activity:
Forward    View Document
Description
BECPL/HSPCB/3117 Date :- 31.07.2017 To The Regional officer Haryana State pollution Control Board Ballabgarh Region Faridabad -2, Haryana Subject : Show cause notice 017FDBBCTOA/W/HWMSCN3588096 dated – 28.07.2017 Dear Sir This is reference to above said show cause notice 017FDBBCTOA/W/HWMSCN3588096 dated – 28.07.2017. we would like to have your kind attention on followings. 1. Enclosing herewith copy of agreement with registered oil recycler. 2. Enclosing herewith copy of HWM return. 3. Enclosing herewith copy of CA certificate as per the previous. Kindly acknowledge the receipt of the same & grant us consent renewal as early as possible. Thanking You, Yours faithfully, For Bhunit Engineering Co. Pvt. Ltd
Note By: 13FDBB582706 (Industry)
Date Time: 31/07/2017 14:33:56 PM
Forwarded To: SEE II

Activity:
Forward   
Description
Note By: Chand Saini (SEE II)
Date Time: 02/08/2017 09:51:13 AM
Forwarded To: Regional Officer

Activity:
Forward   
Description
Inspect the site and submit report.
Note By: Vijay Chaudhary (Regional Officer)
Date Time: 02/08/2017 20:09:01 PM
Forwarded To: AEE II

Activity:
Forward   
Description
HO level case :-Unit is involving in manufacturing of auto parts from pressure die casting from Aluminum ingots and Aluminum extraction from scrap falls under the orange category. The unit has applied for regular consent to operate under Water Act & Air Act upto 31-03-2017. Now on 27-04-2017 the unit has applied for renewal of consent. The unit has submitted the 300% additional fees of Rs. 90,000/- and consent fees of Rs. 30,000/- for 01 year along with performance security of Rs 2.0/- lacs . The unit is not generating/discharging any trade effluent. Therefore, A/R is not required. Sample of air emissions has been collected and as per latest A/R of air emissions for the year 2017-18, parameters are within limits (copy enclosed). Unit has provided APCM for the furnace which is structurally adequate and functioning properly. The unit is not covered under HWM Rules. The unit has provided canopy on the 325 KVA DG set & noise monitoring report is attached herewith. In view of above facts, CTO under Water Act & Air Act and authorization under HWM Rules, for the period 27-04-2017 to 31-03-2018 may be granted to the unit with general terms & conditions.
Attached Letter:
Letter Attached By Officials
View Letter
Activity:
Verification Closed    | View Verification Report   |
Description
Note By: Smita Kanodia (AEE II)
Date Time: 11/08/2017 12:11:32 PM
Forwarded To: Regional Officer

Activity:
Forward   
Description
As recommended by AEE-II, CTO under Water Act & Air Act and authorization under HWM Rules, for the period 27-04-2017 to 31-03-2018 may be granted to the unit with general terms & conditions.
Note By: Vijay Chaudhary (Regional Officer)
Date Time: 14/09/2017 14:56:59 PM
Forwarded To: SEE II

Activity:
Forward   
Description
Case reffered back with the folowing observations. 1.You have recommended authorisation under HWM,whereas field officer in her note dated 1.8 2017 has varified that unit is not covered under HWM Rules.Clarify the matter & submit recommendation accordingly.
Note By: Chand Saini (SEE II)
Date Time: 05/10/2017 18:10:10 PM
Forwarded To: Regional Officer

Activity:
Forward   
Description
Please check and put up.
Note By: Vijay Chaudhary (Regional Officer)
Date Time: 10/10/2017 20:22:27 PM
Forwarded To: AEE II

Activity:
Forward   
Description
Its written that The unit is not covered under HWM Rules is due to typographical mistake. The source of hazardous waste is used oil from D.G set & is covered under HWM Rules. In view of above facts, CTO under Water Act & Air Act and authorization under HWM Rules, for the period 27-04-2017 to 31-03-2018 may be granted to the unit with general terms & conditions.
Note By: Smita Kanodia (AEE II)
Date Time: 11/10/2017 12:43:38 PM
Forwarded To: Regional Officer

Activity:
Forward   
Description
Sir, AEE-II correct the verification report. Unit is involving in manufacturing of auto parts from pressure die casting from Aluminum ingots and Aluminum extraction from scrap falls under the orange category. The unit has applied for regular consent to operate under Water Act & Air Act upto 31-03-2017. Now on 27-04-2017 the unit has applied for renewal of consent. The unit has submitted the 300% additional fees of Rs. 90,000/- and consent fees of Rs. 30,000/- for 01 year along with performance security of Rs 2.0/- lacs . The unit is not generating/discharging any trade effluent. Therefore, A/R is not required. Sample of air emissions has been collected and as per latest A/R of air emissions for the year 2017-18, parameters are within limits (copy enclosed). Unit has provided APCM for the furnace which is structurally adequate and functioning properly. The unit has provided canopy on the 325 KVA DG set & noise monitoring report is attached herewith. In view of above facts, Consent to operate under Water Act & Air Act and authorization under HWM Rules, for the period 27-04-2017 to 31-03-2018 may be granted to the unit with general terms & conditions.
Note By: Vijay Chaudhary (Regional Officer)
Date Time: 21/10/2017 13:13:00 PM
Forwarded To: SEE II

Activity:
Forward   
Description
May grant consent to operate under water act,air act & authorization under H.W. Rules to the unit for the period 27.4.2017 to 31.3.2018 as recommended by RO.
Note By: Chand Saini (SEE II)
Date Time: 22/10/2017 11:02:00 AM
Forwarded To: MS

Activity:
Forward   
Description
Recommended for grant of Consent to Operate the unit under the provisions of Water and Air Acts and authorization under HW & OM Rules for the period from 27.04.2017 to 31.03.2018 with general and specific conditions applicable, as proposed.
Note By: S Narayanan IFS (MS)
Date Time: 22/10/2017 18:59:04 PM
Forwarded To: Chairman

Activity:
Forward   
Description
Approved as proposed.
Note By: Dheera Khandelwal (Chairman)
Date Time: 24/10/2017 17:20:57 PM
Forwarded To: MS

Activity:
Forward   
Description
For further necessary action please
Note By: S Narayanan IFS (MS)
Date Time: 25/10/2017 08:06:54 AM
Forwarded To: SEE II

Activity:
Forward   
Description
Note By: Chand Saini (SEE II)
Date Time: 26/10/2017 16:33:10 PM
Forwarded To: Regional Officer

Activity:
Forward   
Approval/Refusal Status:
Approved
Description
Certificate generated as approved by competent authority.
Activity:
Close After Approval
Description
Certificate generated as approved by competent authority.
Note By: Vijay Chaudhary (Regional Officer)
Date Time: 26/11/2017 16:27:31 PM
Forwarded To: Regional Officer